Tyranny of the backlog

BurningDownTheBacklog-2019-03-14-16-19.jpg

The backlog is a great idea: all the things we think the team will build, or perhaps: things they might build, and it might contain other work, like evaluation or reviews. Yes, the backlog is a great idea, all the stuff the team might do, well perhaps not all, it is seldom complete, after all, as they say “stuff happens”.

The truth is: backlogs have a tendency to grow. All too often I find teams who are struggling under the weight of their backlog. They can’t spare time to do experiments or learn something because there is stuff to do. The backlog becomes a tyrannical ruler and all of it MUST BE DONE.

Look at that hypothetical burn-down chart above. By sprint 15 the team is well on its way to completing all the original work. But the amount of work they need to do is higher than when they started. It is not as if the team have been doing nothing. Look at the next chart, it shows how, most weeks, more work is added than is done.

DoneVAdded-2019-03-14-16-19.jpg

To my mind finding more work isn’t a problem, indeed teams should be finding more work. Problems stem from the fact that backlogs – and tracking mechanisms like burn-down charts – try to full-fill competing needs.

  1. The backlog is used as a store of ideas for work to do. This makes sense, you can’t do everything today so postpone some to the future. A backlog allows you t move some things from peak time to off-peak, although software development teams rarely seem to see off-peak time.

Plus, having a backlog makes it easier to say:

“Thanks for your suggestion Fred, I’ve added it to the backlog, I’ll let you know when we get to it.”

Rather than:

“Thanks for your e-mail Fred, we deleted it once we stopped laughing.”

It makes sense to give a new idea a quick once-over. But doing a proper analysis is time consuming:Discussing what is being asked for takes time, as does setting acceptance criteria are. And then there is business value to assess and other work priorities to consider. Therefore, put it in the backlog and do all that later (if it ever gets scheduled.)

Without a backlog we would be forced to make a binary decision: do it and do it now or reject it.

In fact the backlog can become a natural filter: as stories age in the backlog some items will jexpire. Unfortunately many Product Owners don’t feel they have the authority to delete old requests so the backlog grows and grows.

I call such a “constipated backlog”: work goes in but very little comes out. When the only way for items to leave the backlog is by doing them the rate of return falls.

  1. The backlog fills another role because so many teams are still expected to meet project success criteria which ask for “everything to be done.” The backlog becomes a tyrant when people believe that one day it will all be done. Worse still, some people plan using this assumption.

People want to know when “it” will be done, how long it will take and how much it will cost. It takes time to answer those questions and if the backlog is growing any answer is going to be wrong.

In fact, it is probably wrong to think everything will ever be done. Unless one freezes the backlog and refuses to add new work then it is likely that low value items will be postponed while new, more valuable items, will take priority.

As an industry we need to drop the idea that a backlog will ever be done: the backlog as repository of ideas is at odds with the backlog as a measure of completeness.

Think about it this way: some of the items in the backlog are very valuable. Some items are worth very little. Some will cost more effort than the benefit they bring. If we do everything then the low value and the high value will all get done. Conversely, if we encourage new ideas and weed-out as many low value items as possible our rate of return will be higher.

But very few teams follow this model. Many more teams are slaves to the backlog, and their quest for an empty backlog is doomed.


Like this post?

Like to receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

Tyranny of the backlog Read More »

An (agile) coach’s dilemma

iStock-521796758s-2019-02-13-14-54.jpg

I’d never met the team before. It was a small company in Cornwall and the big boss man was away on holiday that week. They took me upstairs to the meeting room. We talked for about an hour and I could tell there was something on their mind.

Eventually one of them asked:

“we have this question we’ve been talking about for ages we’d like you to help with.”

This was it, the $64,000 question.

“Ask” I said.

“Well… should we be using source code control?”

To some of you this might sound funny, to others shocking, but believe me, on average I meet one team a year who don’t use source code control. On this day I had two voices, one in each ear.

The voice in my left ear said:

“You are only a coach, you are here to help them make their own decisions. Talk about their goals, what they want to achieve, find out if they think source code control could help them. Let them explore why it might be the wrong choice.”

The voice in my other ear said:

“Jesus Christ…”

On the one hand the (agile) coach is there to help the team reach their best. The coach isn’t there to tell them what to do, the people – the team – are the experts in what they do, and they are self-organising. The coach is there to help them unlock their superhero powers.

On the other hand: the coach has done this before. If they are any good they have not only worked with many teams before and read many reports in books and blogs but they wrote the reports, their teams are in the case studies. The team may well be experts in Java, JavaScript, inertial navigation, limb-replacements or whatever but the coach is the expert in agile. The coach is there to teach.

If you’ve read about coaching in other contexts you might recognise this as a question of non-directive coaching v. directive coaching. Agile, and agile coaching has never really come to terms with that differentiation.

As a coach you have next to no authority, all you can hope is that the coachees come to respect you and trust you enough to follow your suggestions. But then, maybe you shouldn’t be suggesting anything?

But if you claim to know anything – about coaching, about agile and heaven forbid software development – is it right to hold back on them when you know the answer? Isn’t it dishonest not to say what you know – or at least sincerely believe – to be true?

And if you can see what they need to do, don’t tell them but work to help them see that answer, well… thats just manipulation isn’t it?

When do you allow free will and when do you railroad?
When do you unlock self-knowledge and when do you teach?
When do you let people take decisions you can see are mistakes?
When do you know facts that will help? And when are you just full of the same biases as everyone else?

Take the documentation question: classically trained developers who have never worked in high-performing teams commonly see documentation as the answer to so many questions:

Question: How do we make sure requirements are clear?
Answer: Documentation

Q: How do we help new recruits find their way around the system?
A: Documentation

Q: How do we keep track of the code design?
A: Documentation

Q: How do we agree which bugs to fix?
A: Documentation

Q: How do we communicate with customers?
A: Documentation

Some people just don’t know what they don’t know.

I too was trained that documentation was the answer to these questions and more, I too saw the lack of documentation as a major problem when I started work somewhere new. It took time (and Railtrack PLC) for me to realise documentation wasn’t the answer, it was John Seely Brown and Julian Orr who help me to realise documentation was a problem, and it took Capers Jones to make me see the cost of documentation.

But should I impose my view of documentation on a team? – should I even be making them see the world as I do?

Ultimately the team are self-organizing. They have the right to document, or not to document, and they can decide to ditch the coach. (Being an agile coach can be a high risk profession.)

Ultimately they are allowed to self-organize long (seated) morning meetings. They are allowed to reject TDD, BDD, CD, CI and just about every other agile practice.

And you know what? They could be right.

Coaches need to be self-aware and with that self-awareness comes self-doubt. Just because a team doesn’t follow the normal rule book doesn’t mean they are wrong. They could have a better solution. They could have a solution that works better in their context.

Back in Cornwall, I paused for a few moments while the angels on my shoulders argued their case. Then I said:

“Put it like this, without source code control I wouldn’t get out of bed in the morning.”

With that question settled I moved onto the issues. What problems would it create? Why wouldn’t you use source code control? What is the worst that could happen? What difference would big boss man see?

Arse about face really but it worked. The following morning I walked into their office and found them checking everything in.

Eight years later that small company has grown more than 20 fold: would they have done that if I had answered differently? Might they have done even better? Did I make a difference or was it all them?

But I still face dilemmas like that everyday I’m “coaching”.


Like this post?

Like to receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

An (agile) coach’s dilemma Read More »

Throwing mud at a wall

iStock-515277657small-2019-02-6-18-44.jpg

Throwing mud at a wall is a metaphor I use again and again. As a description of what I do and as a metaphor for creating change in organizations.

When you throw mud at a wall most of it falls off immediately. Some will stick for a little while then falls off. A little sticks permanent. Perhaps too little to see. So you throw some more and the same thing happens. Sometimes it looks like no mud has stuck but actually a little bit has even though you cannot see it.

Every time the mud falls off it is sad, even depressing but you have to keep throwing. Thats all you can do really.

You keep throwing, the more mud that sticks the better the chances that more will stick next time. Gradually, slowly, sometimes imperceptibly the mud builds up. As long as you can maintain your energy, stamina and resolve, you keep trying.

It can be depressing. Sometimes you can stay positive and you give up. Perhaps you move on to another wall.

In this blog, in my books, in my tweets (thankfully vastly reduced recently) I throw mud. Yes, I am a mud slinger, some people think I doing it with bad intentions. But my intentions good, I see a world that needs to think differently.

And when I’m hired to help companies I see it much the same way. I throw a lot of ideas at people, I suggest lots of changes, I throw mud at a wall and most of my ideas fall off. Much of what I suggest gets ignored. No matter how much I talk I have no authority, people are free to ignore me.

Some places I’m very successful, some less so. When I’m inside a company I try to be a bit more directed with my mud throwing, and I limit the ideas I’m throwing. But still it is a question of stamina and resolve. Some places are just more receptive to new ideas than others.

And actually, this is my model for all organizational change. To my mind, all us “change agents” (yes I hate the term too) can do is make suggestions. Throw ideas at people, if they like the ideas, if they think the idea might help then they might adopt it. But they don’t have to. It is hard to force change on people, if you try they may say they will change, they may go through the motions but sooner or later – when your back is turned – the mud will fall off.

Individuals have free will. Most of them want to work as best they can. So if some “agile coach” turns up with an idea workers don’t think will work they are free to ignore it.

I’m not a great believer in authority: just because you are blessed with the title “Manager” (or “Director” or “Executive” or even “President”) doesn’t mean people will fall your orders immediately and without question.

The best way of getting your mud to stick, getting your ideas and changes adopted is to help people understand how such changes will benefit them as individuals. Benefit them in the work they do, the quality of their life-work balance and the pride they feel in work.

Conversely, there are some people, even some organisations, who are totally unreceptive to mud. They go out of their way to avoid it. It is hard enough throwing mud which doesn’t stick, but when people don’t want it to stick, well, I’m probably better off going elsewhere.


Like this post?

Like to receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

Throwing mud at a wall Read More »

Error handling omitted for brevity

throw-2019-01-9-15-34.png

Q: What is the difference between programming in college and programming in the real world?
A: Error handling

Do you remember when you were learning to program? Do you remember those text books you had back in college? And do you remember what they said about error handling?

As I remember it most of what they said about error handling was:

        /* error handling omitted for brevity */

Or perhaps:

        (* error handling omitted for brevity *)

Back in college error handling hardly got a mention, and if it did it was to abort the program. Yet in the real world 80% of what you program is error handling, or rather exceptions, the corner cases, what happens when things go wrong.

I’ve been saying this for years but this week I realised how shocking this was.

A couple of years ago a paper entitled “Simple Testing Can Prevent Most Critical Failures: An Analysis of Production Failures in Distributed Data-Intensive Systems” (2014, you know its an academic paper because it has 8 authors)) was momentarily famous on Twitter. I grabbed it and had a quick read but this week I had reason to go back and look at it again. In the process I found a 20 minutes video presentation by one of the authors.

To cut a long story short, the authors looked at the source code for large open source applications (Cassandra, MapReduce, etc) and software failures. Among various finding they reported:

  • Finding 1: “A majority (77%) of the failures require more than one input event to manifest, but most of the failures (90%) require no more than 3” – so even if didn’t happen very often, they were difficult to simulate in system testing
  • Finding 9: “A majority of the production failures (77%) can be reproduced by a unit test.” (Yes the reoccurrence of 77% is suspicion but I think it is an improbably but genuine co-incidence, please read the paper or watch the video before you fault the paper on this.)
  • Finding 10: “Almost all catastrophic failures (92%) are the result of incorrect handling of non-fatal errors explicitly signalled in software.”
  • Finding 11 “35% of the catastrophic failures are caused by trivial mistakes in error handling logic — ones that simply violate best programming practices; and that can be detected without system specific knowledge.”

The authors even created a tool to scan code for some of these problems. In many cases they found code like:

catch (…) {
        // TODO
}

catch (Exception e) {
        /* will never happen */
}

My old jibe about error handling looked very real.

This morning I pulled some old books off my shelves and was shocked by what I found:

First the book I was prescribed at not one but two University programming courses: “Problem Solving and Structured Programming in Modula-2” by Elliot B. Kaufman (1988).

I can’t find “Error handling omitted” in this book, my memory was wrong but the book is worse. I can’t find any error handling to speak of! I found one example which returns a boolean success/fail flag but there is no discussion of what to do with it. “Error handling” is not even in the index, let alone the table of contents – actually “Error” isn’t even there.

Each chapter ends with a “Common Programming Errors” section but this section is mostly about compile time errors.

Next I looked at the silver book, Wirth’s “Pascal User Manual and Report” (1991). I can only find two references to “errors” (nothing to exception). Both these references are in the report section and don’t say anything about how to program error handling.

As I looked at more old books I noticed how they just assumed everything worked well.

K&R is slightly better – “The C Programming Language” by Kernighan and Ritchie (1988) that is. Most of the examples here do check for errors, then printf. Sometimes that is it, sometimes there return 0 or break. On page 164 they say:

“We have generally not worried about exit status in our small illustrative programs, but any serious program should take care to return sensible, useful status values.”

In other words: Error handling omitted for brevity.

Moving away from the introductory books I turned to what might be the longest single volume technical book I ever read. A book I quoted as a bible, a book who’s author I still put on a pedestal: “Large Scale C++ Software Design”, John Lakos (1996). While John does say a bit more about error handling it does not feature in the index and there is no dedicated section to it. Looking at it now I am in disbelief, how could a book a large scale C++ not have at least one chapter on error handling?

Of the books I look at this morning only Kernighan and Pike’s “Practice of Programming” (1999) gave any coverage to error handling. And that isn’t saying much.

OK, these are all ancient books. Have things changed? – you tell me.

I hope more recent books, in more modern languages have got better – and my old (1999) copy of “Learning Python” (Ascher) contains a whole chapter on exceptions as does Stroustrup’s “C++ Programming Language” (2000).

But I am sure error and exception handling hasn’t got any simpler. I can’t believe that JavaScript, PHP, Swift, and simiar. have somehow made the problem go away. “Throw exception(blah, blah, blah)” might be a great improvement over “return -1” but I can’t imagine handling these cases has got easier.

Based on the “Simple Testing” paper improvements in training programmer in error handling need to be redoubled.


Like this post?

Like to receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

Error handling omitted for brevity Read More »

The power of small declines

DeclineGraph-2018-12-13-10-41.jpg

Last year I wrote about the power of 1% improvement, and how powerful this can be when that improvement occurs frequently. For example, if a team improves 1% a week then over the course of 50 weeks (a year) they would improve by over 62%.

A few days ago I had a revelation: the opposite is also true.

If a team enters a downward spiral then a 1% decline in productivity each week has similar effects but in the opposite direction. In fact, as I think about this I see more and more occasions where a team can loose small amounts of performance which actually saps their productive capacity. Like the frog in hot water they don’t realise they are cooked until it is too late.

The graph above shows what happens to value-add over a year when a team is 1% less productive each week. The blue bars show how value-add falls each week. The red line shows how each week the team declines slightly compared to the week before.

That the red line get higher seems odd but it makes sense: each week the team is 1% less productive than the week before. So at the end of the second week the team is 1% less productive than they were in the first week. At the end of week 50 they are 1% less productive than week 49 but only 0.62% more less productive than week 1 because the 1% decline was from a lower total. Getting worse slows down because the team are worse!

At some point the value-add ceases to justify the cost of the team. But as these changes are very gradual that is going to be hard to see.

Why might this happen? – lots of reasons

First off there are the corporate drains on productivity. Consider corporate security processes: think about passwords alone, the need to change passwords regularly, have longer and longer passwords, have different passwords on different systems, and so on. Sure cyber security is important but it can also be a drain on productivity.

Then there are the other hassles of working almost anywhere: finding meeting rooms, booking meeting rooms, setting up webex conference calls, “cake in the kitchen”, restrictions on internet use – whether it is limited access, site blacklists, or authorised “white list” sites only.

It is easy to see how a large corporate can gradually drain a team. But there are other reasons.

There are personal drains on productivity too. Consider internet use during work time. The likes of Facebook, LinkedIn and Twitter which aim to keep you on their sites as long as possible. Using LinkedIn is almost a necessity in modern work – got a meeting coming up? someone applied for a job? looking for a lead? – but once your in, Microsoft wants to keep you there.

Then think about your code base: is the code getting better or worse?

  • Easier to work with or harder to work with?
  • Do you write an automated test for every change? Or save time today at the cost of time tomorrow, and the next day, and the day after, and …
  • Do you take time to refactor every time you make a change? or are you constantly kludging it and making the next change slightly harder?

Notice here I’m not talking about those big time consuming changes that happen occasionally: new employees, reorganisations, mergers – things that happen occasionally, take a chunk of time but finish.

So, is your work environment getting a little bit better every week? or a little bit harder?

If we think at the “very little” level it is unlikely that things are the same as last week. Staying the same will be hard. Things are probably a little bit better or a little bit harder. Extend that over a year and – as the theory of 1% change shows – things are a lot worse, or maybe a lot better.

What is important is the trend, and the trend is going to be set by the culture. Do you have a culture of small improvements? Or an acceptance of small degradation?

Finally, because there are so many minor factors that can sap your productivity capacity then it is quite likely that if you aren’t getting more productive then you are getting less. In other words, you need to be working to improve just to stand still.

The power of small declines Read More »

Money talks: A tale of two change programs

iStock_000005509580Small-2018-11-21-13-12.jpg

Like many in the agile community – or what sometimes gets called the agile industrial complex – I am all for piecemeal adoption, small scale before large scale, get good at doing stuff then expand it out… – what else would you expect from Mr Diseconomies of Scale?

The “start small” and grow might even be regarded as the canonical approach to agile implementation. But from time to time I run across something that makes me wonder…

Four or five years back I got involved with an agile transformation programme at a large financial institution, not a bank, more of a mass market asset manager. I was attached to a small team trying to make the whole company agile.

The coaches viewed themselves as a guerrilla movement, changing the organization from within. They had some success, there was a bunch of stuff the agile teams and the coaches were doing wrong but that is another story. This was a licensed insurrection.

As is often the case, this team found it lacked the ability to ask the big questions and get people outside the team (often the higher ups) to engage or change themselves. The organization wanted agile down in the engine room – at the code face – but they didn’t want to rethink how they set requirements and approached projects. The whole organization was chronically project driven, obsessed with long term planning and offshore development. Economies of scale thinking ran riot.

Because the agile change was at the team level the product owners lacked authority to make real decisions – like not delivering functionality. Yes the organization wanted to “be agile” but the management cadre didn’t see any need to change their own behaviour.

One day I met two men who ran the company’s “Software Process Group.” They were guardians of the formal process and “working practices”. My immediate reaction was that they wanted to kill agile and stick with ISO-9000, PRINCE2, CMMI and certified approaches. They scared me. But actually they were very clued up. They got agile. They saw it was better than the current process.

These two had no role in the agile transformation, their role was to ensure the company kept its CMMI level two certification. This was really important to the company because this allowed the company to do business. They told me a story…

During the previous 20 years the company had grown large, very large, by buying up competitors and companies in related markets. These companies had been thrown together and costs stripped out. One day the financial regulator came to the company and said:

“We have been examining your IT functions. They are not fit for purpose. If you don’t fix it within 12 months we are going to withdraw your license to do business.”

Shit hitting the fan doesn’t come much bigger than this.

The company went to IBM and said “Help! – Fix it – we’ll will pay anything.”

IBM flooded the company with people. IBM imposed a process – a traditional CMMI compliant process. IBM changed the company, not just the programmers but everything. The company did as IBM told them.

And don’t imagine it was cheap. I bet that the change and IBM fees were on the agenda at every board meeting during that period. The men I had met were the remnants of that programme, they worked for the company not IBM, their job was to ensure the company maintained accreditation and the financial regulator wouldn’t have cause to come back.

Now contrast this with the piecemeal, small scale, bottom-up change that us agile folk are so fond of. Time and time again we get stuck: “the business won’t change”, “we can’t get access to the senior people”, “existing processes and expectations are unassailable”, “projects are killing us” and so on.

I’m sure IBM faced many of those same problems but they had one big advantage: They were expensive.

OK, they had a second: the loss of license would destroy the client company. But when threatened people often respond by sticking with that they know so maybe it was a double edged sword.

Because IBM were expensive they had access to anyone they wanted access too. Because they were expensive they had authority. And if someone didn’t want to make the changes IBM suggested then IBM could simply ask the next person up.

Once again money is information: by spending lots of money with IBM the company was signalling it really wanted these changes to happen.

Agile changers may not like big change, they may point to the inherent risks, they may point that use of authority conflicts with self-organization, they may understand that diseconomies of scale rule and they may point to a bunch of other risks.

But they should also note one clear advantage: a big expensive change programme brings authority all of its own.

Money talks: A tale of two change programs Read More »

Agile won the war but lost the peace

iStock-856693018Medium-2018-11-8-16-53.jpg

“I’ve spoken of the shining city all my political life, … in my mind it was a tall, proud city built on rocks stronger than oceans, wind-swept, God-blessed, and teeming with people of all kinds living in harmony and peace; a city with free ports that hummed with commerce and creativity. And if there had to be city walls, the walls had doors and the doors were open to anyone with the will and the heart to get here. That’s how I saw it, and see it still” President Ronald Reagan, Farewell to the Nation, January 11, 1989

Back in 2001 when the word agile appeared it was a manifesto – a set of ideas, the term “agile” also served to group a bunch of tools and techniques which could make software development “better.” More importantly to my mind, it painted a picture of a shining city on a hill we all wanted to live in.

Agile was a place you wanted to go, it was a journey you wanted to make, it offered hope. More important as the tools – sprints, stand-ups, etc. – and approaches – just in time, last responsible moment, test first – were the stories agile people – including myself – told. These were stories of a better world, of that shining city on the hill.

And not unimportantly, in a world of search engines “agile” gave you something to search for. Before agile you could search “make my software development team better” or “software development process improvement” but what you got was a very mixed offering. AltaVista (and the young Google) would suggest links for CMMI, or ISO-9000, or vendor tools to “fix it”, or proper design, or… there was no coherent message. Most of these ideas resolved around senior people making big decisions and then imposing them.

Then along came agile: it offered to involve everyone, everyone made decisions, everyone was happy and we could all go to that shining city on a hill – more than that, we all had an important part to play in building that city.

Today everyone is agile. Nobody is promoting traditional (“waterfall”) working, CMMI, PMI and everyone else has incorporated agile (to some degree). Not being agile is about as popular as leprosy.

But very few of us have reached the shining city on the hill.

Along the way agile has been watered down, in becoming compatible with everything else it is less different, it is less attractive, fewer workers are motivated to take the journey. And as “the powers that be” have found ways to bring control-and-command back to teams (maybe in the name of scaling) fewer people are invited to help build the city.

Ironically, as we (the agile community) has made agile management friendly we have made it less worker friendly. Today senior managers “get agile” and want their organisations to be agile. But those at the code face seem to have less and less motivation. And those in the middle… sometimes they seem to want to change just enough to declare success but no so much that things really change.

For some people agile has become completely discredited – I wrote Why do Dev’s hate agile? last year and I’m presenting it in London next week. Agile isn’t a shining city on a hill, agile is trench warfare.

And Googling “agile” presents a long long list of links with less and less coherence.

Agile won the war. Agile is respectable and everyone is agile now. Big business rush to be agile, Governments want to be agile, blue-chip consultancies will sell you agile.

But agile lost the peace.

While many say they are agile, few software developers live in a shiny city. The place they live in might be better than the place they came from but it doesn’t live up to the dream many of us shared 15 years ago. Agile has become an excuse for failure and a thing to be imposed.

The thing that passes for “agile” today is too often a watered down version of the original dream. Worse still, we don’t have a word to describe that shining city we all want to get to. Russians have an expression for this:

“We wanted the best, it turned out like always.” Viktor Stepanovich Chernomyrdin, Prime Minister Russia, 1998-1999

Me? – I still dream of that shining city on the hill, I still believe agile is the right way to get there, I still wave the flag for agile but more and more I feel the need to explain myself and tell people that the agile I dream of is not the agile they may experience.


Receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

Agile won the war but lost the peace Read More »

More Continuous #NoProjects questions

QA-2018-10-24-14-20.jpg

Three short questions and answers to finish off my series of left over questions about #NoProjects, #NoEstimates and the Continuous model.

Q4: How do we prioritize and organize requests on a product that are from opposite business owners? – for example legal (who wants to reduce the risk and annoy more customers) and sales (who want to increase the features and simplify life) can be arbitrated in a backlog?

You can think of this as “which is worth more apples or milk?” It is difficult to compare two things which are actually different. Yes they are both work requests – or fruit – and each can make a case but at the end of the day you can’t make everything number 1 priority.

In real life we solve this problem with money.

Walk into your local supermarket. Apples, oranges and milk are both price in the same currency, sterling for me, Francs for the person who asked this question, maybe Euro’s or Dollars for you. So if we can assign value points to each request we are half way to solving the problem.

Now sales will argue that without their request there is no real money so whatever they ask for is worth more. And legal will argue that nobody wants to go to jail so their request must be worth more. You can set your analyst to work to calculate a value but a) this will take time and b) even when they have an answer people will dispute it.

Therefore, I would estimate a value – planning poker style. With an estimates value there is no pretence of “right” or “correct”. Each party gives a position and a discussion follows. With luck the different sides converge, if they don’t then I average. Once all requests are valued you have a first cut at prioritisation.

Q5: How to evaluate the number of people you need to maintain software?

I don’t. This is a strategic decision.

Sure someone somewhere needs to decide how much capacity – often expressed as people – will be allocated to a particular activity but rather than base this on need I see this as another priority decision. If a piece of software is important to an organization then it deserves more maintenance, and if it is not important it deserves less.

You could look at the size of the backlog, or the rate of new requests and contrast this with the rate at which work gets done. This would allow you to come up with an estimate of how many people are needed to support a product. But where is the consideration of value?

Instead you say something like: “This product is a key part of our business but the days of big changes are gone. Therefore one person will be assigned to look after the software.”

If in three months more people in the business are demanding more changes to the software and you can see opportunities to extract more value – however you define value – then that decision might be revised. Maybe a second person is assigned.

Or maybe you decide that maintaining this product isn’t delivering more value so why bother? Reduce work to only that needed to keep it going.

Q6: How do you evaluate the fact that your application becomes twice as fast (or slower) when you add a new feature in a short period of time?

Answering this question requires that the team has a clearly defined idea of what value is. Does the organization value execution speed? Does the organization value up-time? Does the organization value capacity?

Hopefully some of this will have come out of the value estimation exercise in Q4, if not the analysis is just going to take a bit longer. The thing to remember is: what does the change do for the business/customers/clients? Being faster is no use in itself, but doing X faster can be valuable.

The real problem here is time. Some changes lead to improvements which can be instantly measured. But there are plenty of changes where the improvements take time to show benefit. Here you might need to rely on qualitative feedback in the short run (“Sam says it is easier to use because it is faster”). Still I would keep trying to evaluate what happens and see if you can make some quantitive assessment later.

Notice that Q4 and Q6 are closely related. If you have a clear understanding of why you are doing something (Q4) then it becomes easier to tell if you have delivered the expected value (Q6). And in trying to understand what value you have delivered then you refine your thinking about the value you might deliver with future work.

Another feedback cycle.


These questions concludes the series of question carried over from the #NoEstimates/#NoProjects workshop in Zurich – see also How should we organize our teams?Dealing with unplanned but urgent workHow do we organise with a parallel team? – if you would like me to answer your question in this blog then please just e-mail me.


The #NoProjects books Project Myopia and Continuous Digital discuss these and similar issues in depth and are both available to buy in electronic or physical form from Amazon.

CDMyopia-2018-10-24-14-20.jpg

More Continuous #NoProjects questions Read More »

Dealing with unplanned but urgent work

YellowUrgent-2018-10-3-09-36.jpg

3) Maintenance and Evolution
To keep a product alive, we choose backlog stories that will bring value, and do them one after the other.
But… as support of the application may take a huge part the work. And when the problem is critical, there is nothing you can do but stop what you do and fix it. This can blow any estimation.
How do you deal with firefighting in a #NoProjects world?
And techniques to avoid it.
How does #NoProject and DevOps work together?

Let me take the last part of this question first. Operations has never been plagued by the project model the way development has. When does a SysAdmin ever say “The project is finished so I’m not going to restart the server” ?

DevOps (aka Continuous Delivery) and Continuous Digital are a natural fit. The team is responsible and accountable: writing the code, deploying it and supporting it there after: “You built it, you operate it” as DevOps people like to say.

Of course the team needs to contain all the skills needed to service this approach. That might mean having an individual specialist on the team or it might mean that team members have multiple skills. A Continuous team is not just a DevOps team, it is also a Business-Technology team – or #BizTech to coin a hashtag. (This week I heard such a team called a BizDevOps team. That is one portmanteau too far for me.)

Which brings us quite nicely to the first part of this question: how do you manage – and perhaps even plan for: unplanned work?

What I would like to happen when unplanned work appears is that it is written on a card and placed in the backlog. It then takes its place with all the other possible work. But… as the questioner states: this work can’t wait, it is urgent.

Unplanned but urgent simply needs to be done. Quite possibly other work, less valuable work or work which is not time critical may even be interrupted.

At this point I was about to refer readers to an old blog post about Yellow Cards. But it turns out that I never wrote that post. Despite talking about Yellow cards for years I’ve never blogged about them. I wrote about them in Xanpan but for some reason or another I never wrote the blog… so here you go…

When a team is mid-sprint and unplanned work appears the team should:

  • First ask “Can this work wait?” – If so then write it on a regular card and put it in the backlog
  • If not then ask, is this more valuable than work we are doing now? – If not then someone needs to find the source of the request and explain why is isn’t going to get done.
  • Assuming it is urgent then it gets written on a Yellow card.
  • If it is really really urgent then someone drops what they are doing and works on the yellow card immediately.
  • If it can wait a little while then the next person who finishes their current work picks up the card and does it.
  • Once the yellow card is done mark it as done as with any other card and work continues as it was before.

Accepting unplanned work into a sprint impacts the other work the team is doing. I’m not a big fan of the commitment protocol so to me it is no big deal if this work displaces something else. But if your team are expected to hold fast to hard commitments while dealing with unplanned work then you have a problem, call me, we need to talk more.

At the end of the iteration we can look at the cards and reason about them. Now we can see the work we can manage it and decide what to do about it.

I count up the yellow cards – and all the planned work cards. That allows me to calculate a ratio of planned versus unplanned work. (Sometimes teams put a retrospective points estimate on a yellow but doing a card count is often sufficient.)

This can be tracked over time – graph it, make it visible again. Now we can look at the work and the pattern of work, reason about it, maybe do some root-cause analysis. Perhaps:

  • Perhaps much of the urgent work isn’t really so urgent, perhaps the team should push back more. Maybe the team, or one of the team leaders, needs to the authority to say No.
  • Perhaps most of the unplanned work comes from a particular person. Maybe this person doesn’t realise the impact of their unplanned requests, or maybe they need to be included in the planning process, or … a million other reasons.
  • Perhaps the unplanned work is coming from the same sub-system, maybe some remedial work on that sub-system could reduce the amount of unexpected work.
  • Perhaps the unplanned work is just the nature of the business and being responsive is valuable.

Looked at this way we can think about reducing the amount of unplanned work. But also, we can plan for unplanned work.

It is likely that over time a pattern will emerge. One team I know found that 20% to 25% of their work in any sprint was unplanned. They simply planned for 20% less work. They now had the capacity to cope with unplanned work. At the least they could expectation manage stakeholders.

One team found that each sprint they were doing about 20% IT support tasks (new PCs, Word problems, etc.) so they hired a support technician.

Another team who agonised about unplanned work found that actually they only had about one unplanned card a week. Their problem was not excessive unplanned work but the fact that unplanned work tended to have a very high profile in the company.

Teams which find they have very high levels of unplanned work on a regular basis (e.g. over 50% of work for several months) may well decide to adopt a full Kanban system. Indeed, Kanban folk probably recognise my description as a very simple example of quality-of-service and policies.

I say more about Yellow Cards for unplanned but urgent in Xanpan so you might like to continue reading there.


This is the third question carried over from the #NoEstimates/#NoProjects August workshop in Zurich.


If you have any questions about Continuous Digital, Project Myopia and #NoProjects please mail them over and I’ll do my best to answer them in this blog.

Receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

Dealing with unplanned but urgent work Read More »

How do we organise with a parallel team?

Question000009042425XSmall-2018-09-25-15-04.jpg

2) Offshoring – When Project meets #NoProject
In our department, we maintain products, … we deliver small features. In parallel, we have some offshore teams working in traditional project mode
The hard part comes when we need to integrate/merge our code. We have different cycles, schedules and objectives. How do we manage code handover code from offshore? – we feel we are inheriting a pack of legacy and tech debt that is added to our own stack.
No matter the handover contract agreement we set, … they don’t make the right choices for a long term maintenance vision.
They deliver the requested features, it works from a business point of view, but they deliver it in a way that can be difficult to maintain in production.
Of course, they do not maintain it, so they don’t have the experience of it.

This is the second question carried over from the #NoEstimates/#NoProjects workshop in Zurich last month.

While the question is phrased as “working with offshoring” I don’t see this as an offshore specific question. I think the question is about working with a second team, a team which does not hold maintenance responsibility and a team which perhaps doesn’t have the same quality standards as the primary team. I am sure that offshoring – and probably outsourcing – complicate matters because issues need to navigate additional boundaries.

One question in my mind is: if the second team impose such additional costs on the primary team are they actually making more work than they are doing? That is, every hour the primary team spending dealing with the liabilities of handover is an hour not delivering their own work. I’d want to look at that but lets assume the second team are worth it.

Something which worries me here: “No matter the handover contract agreement we set”. Are the second team listening? Are they making an effort to work with the primary team? Or are they ignoring the primary team?

If that is the case then it is a big problem because there is little the primary team can do to fix how the second team work. So a question comes into my mind: are those responsible for having the second team aware of the issues? Would they like to improve things?

If not then, as the second team and those employing them are not concerned, the problem may be unsolvable. The only solution the primary team have is to insulate themselves from the problems of the second team. In the short run that removes the pain for individuals but in the long run it will make things worse.

To my mind it does fall on the primary team to make a case to both groups that they would like to make things better and to work with the second team and management to make things better.

So how do we make things better?

The good news is there is lots that can be done here, there are people changes, process change and technical solutions. The bad news is, there is no silver bullet.

People changes: team members should visit each other.

I know travel budgets get cut but there is a clear case here that if team members could visit each other, understand each other, known each other then they will both work together better and be in a better position to improve things.

Process changes: ask the second team to do smaller pieces of work and deliver more often.

I don’t know the mechanism by which work reaches the second team but someone somewhere is asking them to do things. That person needs to change their requests. Of course, this means moving the second team away from the Project Model and towards a Continuous model.

Technical changes: there are a lot of options here but each of these options is gong to work best if people have visited one another and the process has been changed to lots of little.

So:

  • Have both teams practice continuous integration (if they are not already).
  • Reduce the number of branches, move towards trunk based development.
  • Have both teams practice automated unit testing (preferably TDD) and automated acceptance testing (ATDD).
  • Add static analysis tools to the build.
  • Do manual live code reviews, i.e. developers at one location talk to one at the other location while they do the code review.

None of these changes are unique to the scenario described in the question. They are common quality improvement practices. The only addition I’m making is on the code review, I want the second team to review the primary team’s code, not just the primary reviewing the second. I want this because I want teams to learn from each other.

Hopefully you can spot two themes to my suggestions.

Firstly, I’m treating both teams as equal. That is only fair but it makes sense too. If the onshore team makes the offshore team feel as if they are treated as second class then they will act as if they are second class.

Second, most of my suggestions are straight from the Continuous Delivery playbook: have both teams do lots of small high quality pieces of work and integrate them without delay.

Underlying here is a problem: the second team don’t do maintenance. They have little incentive to do better work and maybe unaware of the problems their style of working is causing.

Now having said all this I might be accused of ignoring the question. The question stated: the offshore team work in project mode. And I’ve just given suggestions which could be considered not project mode. Put it this way, I think changes need to happen one way or another. If the second team want to cling to projects then so be it, but they can still improve their quality as they do so.


If you have any questions about Continuous Digital, Project Myopia and #NoProjects please mail them over and I’ll do my best to answer them in this blog.

Receive these posts by e-mail?

Subscribe to my newsletter & receive a free eBook “Xanpan: Team Centric Agile Software Development”

How do we organise with a parallel team? Read More »

Verified by MonsterInsights